Question:

During the Daily Scrum, a team member says he does not know when his task will be complete a) It is acceptable as the Sprint Review date is far away. b) Replace the Team member with new Team member c) The developers should collaborate to plan alternative steps such as pairing this member with someone else, etc to eliminate the risk of not meeting the Sprint Goal. d) Ask the Scrum Master to mentor the team member on how to estimate the task.

Author: Avinash Upadhyay



Answer:

C) The developers should collaborate to plan alternative steps such as pairing this member with someone else, etc to eliminate the risk of not meeting the Sprint Goal.